Weekly Construction Update

Each week during construction season, we'll be updating this page with information about the progress on our construction projects. Off season updates (November-March) will be less frequent due to less activity.

Trail Construction

3/5/18 - Construction of the three trail segments that were started late last fall are nearly complete.  Final review for compliance with the plans is in process and we anticipate the project to be completed in the coming weeks.  We hope you’re able to enjoy these new segments (west side of Colorado Blvd between Majestic and Iris, north side of Bella Rosa Pkwy between Grand Mesa and Sandpiper including a pedestrian crossing of Bella Rosa Pkwy (CR 20), and connecting segments near the northwest corner of Godding Hollow Pkwy and Silver Birch Blvd) and resurfacing of the Milavec Lake trail.

Later this spring, we anticipate beginning on additional segments to further our communities’ trail connections.  Segments will be added in the northwest quadrant of Eagle Valley, northeast quadrant of Eagle Valley, and two segments in the Angel View subdivision.

Finally, the Town is working with the Colorado Department of Transportation (CDOT) to build trails that provide Safe Routes to School.  These trails will be built along the east side of Ridgeway Boulevard from Angel View to Savannah, provide a crossing of Ridgeway near Lyden Creek Boulevard, and continuing west to Frederick Way, providing a crossing of Frederick Way, and continuing west to Maple Street.  This provides a safe route for students to the south side of Thunder Valley K-8.  Construction is anticipated later this summer.


Tipple Pkwy (CR 16)


3/6/18 - All construction items have been completed. The road is fully open to all traffic with no restrictions. After inspection, a punchlist of final construction items was delivered to the contractor and they have until 4/30/2018 to complete.

Hwy 52/William Bailey Improvements 


8/8/17 - Hwy 52 widening is complete. Check out more information on the improvements on our Colorado Boulevard Improvements webpage.

Pavement Maintenance


3/6/18 - All areas identified in the 2017 Pavement Maintenance Program have been completed.
 

Concrete and Alleyway Maintenance Improvements


8/8/17 -  This project is complete for 2017. 

Raw Water Metering Improvements


9/26/17 - This project is complete. All raw water meters have been installed.

Maple Ridge Development Construction


6/27/17 - The work on Tipple for this project is complete. There is still construction taking place in the area so please be aware of construction traffic in the area.